Back to the list
BASF, Ludwigshafen
Information based on publicly available sources
Note on the Completeness of Project Information
The project information listed on this page usually does not include all requested details. Some information may be missing as it is not provided by the identified sources.
Project
| Location | Ludwigshafen |
|---|---|
| Country | Germany |
| State | Rhineland-Palatinate |
| Operator | BASF |
| Commissioning Year | 2027 |
| Commissioning Status | Under Construction |
Product Details
| Heat Source | Industriell (Waste Heat) |
|---|---|
| Notes on Heat Source | Abwärme aus Steamcracker |
Sink and Source
| Maximum Heat Source Temperature | 75 |
|---|---|
| Sink Type | Industrial Processes |
| Notes on Heat Sink | Dampfbereitstellung für Ameisensäureproduktion, 500.000 Tonnen Dampf pro Jahr |
| Flow Temperature Heat Pump [°C] | 200 |
Technical Data
| Maximum COP Heat Side | 3.3 |
|---|---|
| Thermal Capacity [kW] | 50,000 |
| Heating Output [kWh/a] | 360,000,000 |
| Compressor | No Information |
| Refrigerant |
References
| URL | https://www.basf.com/global/de/media/news-relea… |
|---|---|
| URL access date | Feb. 5, 2025 |
| Reference | Lerch, Tim: Heat Pump Steamcracker 2. Präsentation auf der VDI-Fachtagung „Großwärmepumpen in der Industrie“, 17.09.2025, Berlin. |
Data provided by the Portal for Large-Scale Heat Pumps © 2025 by Fraunhofer IEG is licensed under CC BY 4.0